Year Plan W Plan C
0 ($500) ($1,000)
1 (500) (300)
2 (500) (300)
3 (500) (300)
The two systems are of average risk, so k = 10%. Which to accept?
PVCOSTS-W = -$1,743. PVCOSTS-C = -$1,746
W’s costs are slightly lower so pick W.